Installation of MOL DUFI Poliol laboratory feed
Objectives:
Construction of a medium-voltage supply to the MOL DUFI Poliol laboratory
Challenge:
Construction of the required cable traces in a production plant with a very dense utility network, while complying with extremely strict safety requirements.
Solution:
Construction of a medium voltage feed-in for the MOL DUFI Poliol laboratory with the following content:
– preparation of the design of the work
– Laying of medium voltage cable, with construction of the track
– Installation of 2 1MVA concrete-housed transformer stations
– Laying of 0.4kV outgoing cables, with trail construction
– Integration of new network elements into the existing protection and surveillance system
Result:
After the necessary checks and trial operation, smooth operation of the new feeder network.