Arconic-Köfém Kft. Construction of the electrical station of the K2 factory hall
Objectives:
Arconic-Köfém Kft. Implementation of the electrical power supply of the factory hall K2
Challenge:
To be completed within the tight deadline set by the client.
Solution:
Implementation of the electrical power supply station for the K2 factory hall:
– Manufacture and installation of a 20kV medium-voltage installation of type ZS1 with 11 fields
– Manufacture and installation of auxiliary power systems (DC, AC auxiliary distribution equipment, DC uninterruptible system)
– Construction of 7 transformer chambers, installation of 7 dry transformers of 2500 kVA
– Installation fittings
– Construction of false floor
– Fabrication and installation of metal fencing
Result:
Completion of the necessary check measurements and after successful trial operation, smooth operation of the newly installed technology.
Recent Comments