Howmet Köfém K3 Electricity supply installation

Objectives:

Howmet Köfém K3 Electricity supply development

Challenge:

To meet the tight deadlines set by the client and to comply with strict health and safety regulations

Solution:

Expansion of the production hall AWPE K3 at HOWMET-KÖFÉM site No. 2 – construction of the medium voltage electrical supply with the following content:
– Manufacture and installation of 2 ZS1 20kV units
– Manufacture and installation of 1 meter cabinet
– Manufacture and installation of 2 2.5MVA transformers
– electrical technology installation of transformer chambers

Result:

Ensuring uninterrupted electricity supply to the factory by carrying out the necessary measurements and checks, following the trial operation.