BOSCH Campus Construction of medium voltage power supply

Objectives:

BOSCH Campus Medium voltage power supply

Challenge:

To organise the construction works in a cost-effective way due to the prolonged works

Solution:

Construction of the BOSCH Campus Medium Voltage Power Supply with the following content:
– Electrical installation of 12 transformer chambers
– Manufacture, installation and wiring of 34 medium-voltage SM6 equipment fields
– Fabrication and installation of 4 AC auxiliary power units
– Manufacture and installation of 4 Scada cabinets

Result:

Ensuring the uninterrupted electricity supply to the factory by carrying out the necessary measurements and checks, following the trial run.