BorsodChem Zrt. MDI 6,3 kV medium voltage substation CAPEX reconstruction

Objectives:

BorsodChem Zrt. Reconstruction of the CAPEX branch cells of the MDI 6,3 kV medium-voltage substation

Challenge:

To ensure the uninterrupted operation of the parts of the MDI station not affected by the reconstruction.

Solution:

Complete reconstruction of 5 CAPEX branch cells of MDI 6.3 kV medium voltage substation with the following contents:
– clean painting,
– installation of insulating supporting ironwork, replacement of insulators, busbars and main equipment,
– replacement of secondary panel and secondary cables, refurbishment and painting of cell doors
– integration of refurbished cells into the existing protection and surveillance system

Result:

Smooth operation of the refurbished cells after the necessary checks and trial run.