Budapest Waterworks Gilice Square power house electrical reconstruction

Objectives:

Metropolitan Waterworks Gilice Square Electrical reconstruction of the power house

Challenge:

Ensure water supply to the powerhouse during renovation by providing a provistor solution

Solution:

Electrical reconstruction of the Gilice Square powerhouse of the Budapest Waterworks with the following content:
– main distributor 6 field Eaton xEnergy production
– Auxiliary, aggregator, lighting, switchgear; new and old power house and control cabinets
– on-site construction
– integration of new network elements into the existing plant management system

Result:

With the necessary measurements and checks carried out, smooth operation of the power house with the new equipment.