Design and construction of the electrical power supply for the new Ceva-Phylaxia site in Monor

Objectives:

Design and construction of the electricity supply for the new Ceva-Phylaxia site in Monor

Solution:

Design and construction of the electrical power supply for the Monor site:
– Preparation of a complete construction plan
– Installation of a concrete switchgear station for metering accounting
– Manufacture and installation of a 20kV medium-voltage installation with 5+2 fields Simosec type
– Construction of 2 transformer chambers, installation of 2 2500 kVA dry transformers
– Installation of a 3200 A Siemens aluminium encapsulated rail bridge
– Manufacture and installation of a Siemens Sivacon 0.4 kV 7-span 3200 A distribution system
– In-station track construction, 0,4 and 20 kV cabling
– Manufacture and installation of auxiliary systems (DC, AC auxiliary distribution equipment, DC uninterruptible system)
– Manufacture and installation of SCADA and PLC data acquisition cabinets
– SCADA system programming

Result:

Smooth operation of the switchgear station after performing the required check measurements, tests and trial run.